Work continues to move rapidly on Vanderbilt's new multipurpose facility and recreation center expansion. Just in the last few days, crews have formed the outer frame of the north side of the multipurpose facility with steel beams.

This coming week, 13 trusses, each weighing 28 tons, will be delivered to the site and put into place.

VUCommodores.com will continue to provide updates on the construction progress until work is completed. The multipurpose facility is scheduled to open Oct. 31, 2013 with work completed on the recreation center's enhancements in January, 2014.